As we wrap up the 6th week of demolition, we’re excited to share that the Wheeling Inn has been fully demolished, leaving behind only large piles of debris. While this marks a significant milestone, much work remains, particularly in sorting and processing the rubble. In earlier updates, it was communicated that there were plans to transport debris off-site for processing. However, after careful evaluation, project stakeholders have approved bringing a crusher to the site instead. This decision reduces traffic disruptions and enhances pedestrian safety but will result in a slight increase of noise for surrounding neighbors between 8:00 AM and 5:00 PM. Proper dust and noise mitigation measures will be in place throughout this process. The crushing process is scheduled to begin shortly after Thanksgiving and is expected to conclude before Christmas.
top of page
bottom of page
Comentários